Flexible Job Shop Scheduling Method for Optimizing Mold Resource Setup Time
Document Type
article
Source
IEEE Access, Vol 12, Pp 33486-33503 (2024)
Subject
Flexible job shop scheduling problem
mold resource
setup time
differential evolution algorithm
Electrical engineering. Electronics. Nuclear engineering
TK1-9971
Language
English
ISSN
2169-3536
Abstract
In a practical development environment, completing a job often necessitates the coordinated allocation of multiple resources. However, resource constraints such as molds are rarely considered in the multi-resource job shop scheduling problem. These molds have sequence-dependent setup times and are fully occupied during processing. Therefore, this study focuses on the Flexible Job Shop Scheduling Problem with Mold Resource Setup Time Optimization (FJSP-MRST), which aims to minimize setup time and makespan. Considering the characteristics of mold setup time, this paper introduces a Mold-Machine Double Fusion Insertion Method to optimize the mold-machine usage order and improve the mold change time calculation method. This innovative approach improves the overall scheduling process by efficiently managing the utilization of molds and machines. Furthermore, we propose a Mold-Operation Layer Loading Method to compress setup time, offering a novel strategy for reducing the setup time for mold resources. These two pioneering methods are integrated with an enhanced multi-objective differential evolution algorithm to obtain the optimal solution for FJSP-MRST. Experimental results demonstrate that the proposed methods can render the arrangement of machines and molds under the current process sequence more reasonable and effectively eliminate implicit setup time.