西部寒区高速铁路路基沉降整治措施研究 / Study on Control Measures for Subgrade Settlement of High-speed Railway in Cold Regions of Western China
Document Type
Academic Journal
Source
路基工程 / Subgrade Engineering. (5):53-58
Subject
兰新高铁
路基沉降
袖阀管注浆
挡水墙
反压护道
渗水盲沟
Lanzhou—Xinjiang high-speed railway
subgrade settlement
sleeve-valve-pipe grouting
water retaining wall
loading berm
permeable blind ditch
Language
Chinese
ISSN
1003-8825
Abstract
针对兰新高铁某段路基沉降病害,在现场调查与资料分析的基础上综合分析了沉降原因,实施了路基下部及基底袖阀管注浆、挡水墙及反压护道和渗水盲沟等综合整治措施,并对沉降整治效果进行了评价.结果表明:路基沉降得到控制,达到了治理的目的.
In relation to the subgrade settlement disease coming out in certain section of Lanzhou—Xinjiang High-speed Railway,the settlement reasons were analyzed according to the field investigation and data analysis.The comprehensive control measures,including sleeve-valve-pipe grouting,water retaining wall,loading berm and permeable blind ditch,were carried out at the lower part and bottom of the subgrade,and then the control effect was evaluated.The result shows that the subgrade settlement was under control with the control ends achieved.