Multi-period hedging and coordination in a prefabricated construction supply chain.
Document Type
Article
Source
International Journal of Production Research. Apr2019, Vol. 57 Issue 7, p1949-1971. 23p. 7 Charts.
Subject
*Construction contracts
*Supply chain management
*Maintenance costs
Cooperative game theory
Numerical analysis
Language
ISSN
0020-7543
Abstract
In this paper, a multi-period buffer space hedging coordination between a building contractor (BC) and a logistics provider (LP) is investigated. In order to facilitate the application of the construction lead-time hedging (CLTH) strategy, adopted by the BC, extra buffer space needs to be reserved at LP's intermediate warehouse for contingency usage. This strategy is defined as 'buffer space hedging (BSH)' and it increases the pressure of LP on involving extra storage and maintenance cost. Two coordination mechanisms are adopted for solving this BSH problem. One scheme is by introducing a cost-sharing term. A Nash game model is studied to find the individual optimal decisions. Another scheme is a cooperative game model with proper side-payments. We show that adjusting the BSH amount for each review period benefits the supply chain. Both coordination mechanisms enable a win–win outcome. Especially, if system resources are sufficient, the cooperative game outperforms the Nash game. Numerical experiments further demonstrate that the benefit of the proposed model is more significant under the case with lower unit enlarging/rearrangement cost, higher tardiness penalty and unpredictable and uncontrollable construction process-determined assembled and installed prefabs. [ABSTRACT FROM AUTHOR]